Aluminum cold chamber die casting machines for making door handles

Longhua die casting machines use the finite element software optimization design, the stress distribution is reasonable, effectively improves the casting quality.




Product Item:

Aluminum cold chamber die casting machines for making door handles


Product Description

Cold chamber die casting machine in the process of operation mainly refers to the injection chamber and injection punch is not immersed in molten metal, in the use of the effective quantity of molten metal poured into the injection chamber, and then the injection of a die casting machine.



The productivity of die casting machinesRequirements for maintenance of die casting machine

LH SERIES OF STANDARD PARAMETER TABLE (LH-125T)

ITEMS

UNIT

SPECIFICATION

HYDRAULIC WORKING PRESSURE

MPA

7

CLAMPING FORCE               

KN

1250

SPACE BETWEEN TIE BARS

MM

420*420

TIE BAR DIAMETER

MM

¢80

DIE OPENING STROKE

MM

350

INJECTION FORCE(INTENSIFY)                  

KN

180

PLUNGER LAUNCH DISTANCE

MM

120

INJECTION POSITION

MM

0  --  140

PLUNGER DIAMETER

MM

¢40----¢60

INJECTION STROKE

MM

320

CASTING PRESSURE (INTENSIFY)

MPA

143/92/64

CASTING FIANGE PROTRUSION

MM

10

CASTING FIANGE DIAMETER

MM

110

MAX CASTING AREA UNDER 40MPA

CM2

375

LNJECTION WEIGHT(AL)

KG

1.6

DIE HEIGHT(MIN--MAX)

MM

200~500

EJECTOR FORCE

KN

100

EJECTOR STROKE

MM

80

MOTOR CAPACITY

KW

11

MACHINE DIMENSIONS  (L*W*H)

M

4.5*1.2*1.5

REFERENTIAL MACHINE WEIGHT FOR UPLIFTING

T

4.5

OIL TANK CAPACITY

L

300

PS: WE RESERVE THE RIGHT TO MAKE ANY TECHNICAL IMPROVEMENT WITHOUT FURTHER NOTICE


Requirements for maintenance ofdie casting machine

1. Clean all sundries within the operating range of the machine before starting each time.

2. Carefully check whether the safety protection device and travel switch are normal, and whether the emergency stop button is normal.

3. When cleaning the pressure chamber and punch, do not touch or extend your hand into the pressure chamber.

4. Do not put fire or heat source near accumulator and hydraulic pipeline system.

5. Do not remove, modify and adjust safety protection devices and components at will, and get the support of the machine manufacturer when necessary.

6. Each time the oil pump is started, the "stop" position of each operation switch must be confirmed.

7. Do not clean the electrical box with compressed air.


Contact Us

 





Product Tags kwikset 400t          t410 400t          az 400t          oregon 400t          honda 400t          400t crawler crane          hp laserjet 400t          triumph 400t treadmill          400t mobile crane         

INQUIRY

Contact us for all information about the product


click here to leave a message

leave a message
If you are interested in our products and want to know more details,please leave a message here,we will reply you as soon as we can.